(8)Monday February 4, 2002 - It rained a little today so
we didn't get to work outside much but we did get in a few hours.
I am about 50 feet from finishing clearing the trees for the circle
drive. There is still a lot of clearing necessary for the spray
area for the septic system. I need an area that is about 100' x
150' for that and we are about two thirds of the way through that.
It is going to take some time to burn all the cedars we knocked
down.
()Tuesday February 5, 2002 - The painters did not show up
today. I had to work at my day job all day so I didn't work on the
house but Roy cut some cedar for the railing for the deck and put
threaded connectors on all of the plumbing stub outs.
(4)Wednesday February 6, 2002 - Roy worked on installing
the fittings on the upstairs shower while I worked on the treads
for the stairs. I also installed some cabinets in the shop. The
painters showed up and touched up the trim and caulked and sanded.
(7)Thursday February 7, 2002 - The painters came and sprayed
the trim with Kilz primer. I spent most of the day clearing the
area for the septic system and the circle drive.
(8)Friday February 8, 2002 - I finished clearing all of
the trees for the circle drive and excavating the boulders in the
way. The painters sprayed primer on all of the walls today. I also
glued up a few more stair treads.
(10)Saturday February 9, 2002 - Clayton and I spent most
of the day sorting, prepping and milling the oak for the cabinet
doors.
(6)Sunday February 10, 2002 - I cut plywood and worked on
the corner sink cabinet. I also finished plumbing the upstairs shower
and framed out the plumbing access panels so they can get painted.
Week 34
|